This entry was posted on Monday, November 5th, 2007 at 9:29 pm and is filed under Capital Improvements. You can follow any responses to this entry through the RSS 2.0 feed. You can leave a response, or trackback from your own site.
a creditable community website
CAPITAL IMPROVEMENT PROJECT UPDATE
|
Department:
|
ENGINEERING
|
Project Manager:
|
Suneel Garg
|
Contact Number:
|
623.222.3424
|
|||||
| Right Turn Lane @ Bell & 115th
|
LAST UPDATED:
|
10/3/2007
|
||||||||
|
PROJECT NUMBER:
|
20715
|
CURRENT PHASE:
|
PROCUREMENT
|
|||||||
|
% COMPLETE:
|
40%
|
PROJECT BUDGET:
|
1,100,000.00$
|
|||||||
|
EST COMPLETION:
|
May 2008
|
TOTAL EXPENDED:
|
45,561.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
United Engineering (UE) has been selected to provide the design services. 100% design documents are complete.
|
||||||||||
|
Department:
|
ENGINEERING
|
Project Manager:
|
Nick Mascia
|
Contact Number:
|
623.222.3400
|
|||||
| Fiber Optics - Citywide
|
LAST UPDATED:
|
10/2/2007
|
||||||||
|
PROJECT NUMBER:
|
20718
|
CURRENT PHASE:
|
DESIGN
|
|||||||
|
% COMPLETE:
|
10%
|
PROJECT BUDGET:
|
750,000.00$
|
|||||||
|
EST COMPLETION:
|
August 2009
|
TOTAL EXPENDED:
|
-$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
Consultant contract approved Sept 13, 2007. Design kicked off Sept. 27, 2007.
|
||||||||||
|
Department:
|
ENGINEERING
|
Project Manager:
|
Suneel Garg and Nick Mas
|
Contact Number:c
|
623.222.3424
|
|||||
| Historical Lighting Signage for Original Town Site
|
LAST UPDATED:
|
10/2/2007
|
||||||||
|
PROJECT NUMBER:
|
20735
|
CURRENT PHASE:
|
PROCUREMENT
|
|||||||
|
% COMPLETE:
|
75%
|
PROJECT BUDGET:
|
525,000.00$
|
|||||||
|
EST COMPLETION:
|
December 2008
|
TOTAL EXPENDED:
|
24,837.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
Street Lights: Arizona Public Service (APS) is currently installing the lights and is estimated to complete by end of October.Decorative Signs and Signals: Council approved the purchase order and new vendor issued notice to proceed to supply signs.
|
||||||||||
|
Department:
|
ENGINEERING
|
Project Manager:
|
Suneel Garg
|
Contact Number:
|
623.222.3424
|
|||||
| Cotton Lane Widening (North of Bell Road)
|
LAST UPDATED:
|
10/3/2007
|
||||||||
|
PROJECT NUMBER:
|
20807
|
CURRENT PHASE:
|
DESIGN
|
|||||||
|
% COMPLETE:
|
45%
|
PROJECT BUDGET:
|
300,000.00$
|
|||||||
|
EST COMPLETION:
|
June 2008
|
TOTAL EXPENDED:
|
-$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
The project is placed for bid closing Oct 11.
|
||||||||||
|
Department:
|
ENGINEERING
|
Project Manager:
|
Suneel Garg
|
Contact Number:
|
623.222.3424
|
|||||
| Litchfield Road (Bell Road to Statler Boulevard)
|
LAST UPDATED:
|
10/2/2007
|
||||||||
|
PROJECT NUMBER:
|
20808
|
CURRENT PHASE:
|
DESIGN
|
|||||||
|
% COMPLETE:
|
45%
|
PROJECT BUDGET:
|
1,300,000.00$
|
|||||||
|
EST COMPLETION:
|
May 2008
|
TOTAL EXPENDED:
|
-$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
Improve Litchfield Road from Bell Road to Statler Boulevard a distance of approximately 1/2 mile. 100% plans are complete and approved. Arizona Public Services (APS) is in the process of finalizing the street light plans
|
||||||||||
|
Department:
|
ENGINEERING
|
Project Manager:
|
Suneel Garg
|
Contact Number:
|
623.222.3424
|
|||||
| Reems Road (Waddell Road to Peoria Avenue)
|
LAST UPDATED:
|
10/3/2007
|
||||||||
|
PROJECT NUMBER:
|
20809
|
CURRENT PHASE:
|
DESIGN
|
|||||||
|
% COMPLETE:
|
37%
|
PROJECT BUDGET:
|
9,500,000.00$
|
|||||||
|
EST COMPLETION:
|
July 2008
|
TOTAL EXPENDED:
|
-$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
100% improvement plans are complete. Waiting for the approval from Maricopa Water District (MWD) for the irrigation channel relocation.
|
||||||||||
|
Department:
|
ENGINEERING
|
Project Manager:
|
Nick Mascia
|
Contact Number:
|
623.222.3400
|
|||||
| Traffic Signals
|
LAST UPDATED:
|
10/2/2007
|
||||||||
|
PROJECT NUMBER:
|
29999
|
CURRENT PHASE:
|
Various Stages
|
|||||||
|
% COMPLETE:
|
0%
|
PROJECT BUDGET:
|
7,477,400.00$
|
|||||||
|
EST COMPLETION:
|
Various Stages
|
TOTAL EXPENDED:
|
3,506,008.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
This project has various intersections at various stages of design, procurement, and construction. The detail portion will provide the specific information on each intersection.
|
||||||||||
|
Department:
|
PUBLIC WORKS
|
Project Manager:
|
Terry Lowe
|
Contact Number:
|
623.222.6000
|
|||||
| Public Safety Building
|
LAST UPDATED:
|
10/7/2007
|
||||||||
|
PROJECT NUMBER:
|
20219
|
CURRENT PHASE:
|
CONSTRUCTION
|
|||||||
|
% COMPLETE:
|
99%
|
PROJECT BUDGET:
|
31,701,300.00$
|
|||||||
|
EST COMPLETION:
|
October 2007
|
TOTAL EXPENDED:
|
25,388,175.00$
|
|||||||
|
UPDATE SYNOPSIS:
|
||||||||||
|
The entire construction of the Public Safety Facility is 98%. The last 2% accounts for the punch list and any misc. items that are as of yet unresolved. The Fire Department, the Court and Prosecution were relocated into the Facility in September. The Grand Opening is scheduled for Saturday, November 3rd.
|
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Terry Lowe |
Contact Number: |
623.222.6000 |
|||||
| Lizard Run Pedestrian Walkway |
LAST UPDATED: |
10/7/2007 |
||||||||
|
PROJECT NUMBER: |
20517 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
58% |
PROJECT BUDGET: |
1,023,800.00$ | |||||||
|
EST COMPLETION: |
June 2008 |
TOTAL EXPENDED: |
124,923.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The contractor has completed the mass grading of the site. This involves staking the site to identify the final elevations and the project area then shaping the earth accordingly. Excavation commenced for the installation of the sidewalk and gabion wall. In addition, all drywells for the site have been installed. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Harry Hartman |
Contact Number: |
623.222.6000 |
|||||
| Fire Station #6 |
LAST UPDATED: |
10/7/2007 |
||||||||
|
PROJECT NUMBER: |
20559 |
CURRENT PHASE: |
CONSTRUCTION |
|||||||
|
% COMPLETE: |
100% |
PROJECT BUDGET: |
4,990,000.00$ | |||||||
|
EST COMPLETION: |
August 2007 |
TOTAL EXPENDED: |
4,297,675.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The Grand Opening for the FS306 took place September 22nd. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Harry Hartman |
Contact Number: |
623.222.6000 |
|||||
| Fire Station #5 |
LAST UPDATED: |
10/7/2007 |
||||||||
|
PROJECT NUMBER: |
20602 |
CURRENT PHASE: |
CONSTRUCTION |
|||||||
|
% COMPLETE: |
98% |
PROJECT BUDGET: |
5,870,000.00$ | |||||||
|
EST COMPLETION: |
October 2007 |
TOTAL EXPENDED: |
5,058,992.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The construction of the Fire Station is approximately 95% complete. Final testing and inspections were completed in September. The Fire Department is scheduled to occupy the facility on the 1st of October. The Grand Opening has been set for Saturday, October 13th. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Terry Lowe |
Contact Number: |
623.222.6000 |
|||||
| Surprise Farm Park Development |
LAST UPDATED: |
10/10/2007 |
||||||||
|
PROJECT NUMBER: |
20606 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
39% |
PROJECT BUDGET: |
5,620,000.00$ | |||||||
|
EST COMPLETION: |
January 2009 |
TOTAL EXPENDED: |
305,889.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The modification of the scope of the project for Surprise Farms Park require additional design services to be put forth. These additional services will be brought before council on October 23rd for approval. The modifications to the scope have lead to a delay in the project’s schedule. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Terry Lowe |
Contact Number: |
623.222.6000 |
|||||
| Skate/Bike Park |
LAST UPDATED: |
10/7/2007 |
||||||||
|
PROJECT NUMBER: |
20618 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
28% |
PROJECT BUDGET: |
950,000.00$ | |||||||
|
EST COMPLETION: |
June 2008 |
TOTAL EXPENDED: |
14,172.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The City received the 60% design documents from the designer in September. Comments will be generated by the Project Management Division (PMD) and returned to the designer in October. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Harry Hartman |
Contact Number: |
623.222.6000 |
|||||
| Fire Station #2 Remodel |
LAST UPDATED: |
10/10/2007 |
||||||||
|
PROJECT NUMBER: |
20624 |
CURRENT PHASE: |
PROCUREMENT |
|||||||
|
% COMPLETE: |
75% |
PROJECT BUDGET: |
769,200.00$ | |||||||
|
EST COMPLETION: |
February 2008 |
TOTAL EXPENDED: |
35,138.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The exterior site improvements for the Station were completed in September. Council gave approval to the GMP for the interior remodel which commenced towards the end of the month. Presently, the existing interior partitions are being demolished. Demolishing should continue into October. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Terry Lowe |
Contact Number: |
623.222.6000 |
|||||
| Public Safety Park Development |
LAST UPDATED: |
10/10/2007 |
||||||||
|
PROJECT NUMBER: |
20635 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
39% |
PROJECT BUDGET: |
200,000.00$ | |||||||
|
EST COMPLETION: |
January 2009 |
TOTAL EXPENDED: |
20,000.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The modification of the scope of the project for Surprise Farms Park require additional design services to be put forth. These additional services will be brought before council on October 23rd for approval. The modifications to the scope have lead to a delay in the project’s schedule. |
||||||||||
|
Department: |
PUBLIC WORKS |
Project Manager: |
Harry Hartman |
Contact Number: |
623.222.6000 |
|||||
| Wash Racks |
LAST UPDATED: |
10/9/2007 |
||||||||
|
PROJECT NUMBER: |
20645 |
CURRENT PHASE: |
DESIGN |
|||||||
|
% COMPLETE: |
100% |
PROJECT BUDGET: |
180,000.00$ | |||||||
|
EST COMPLETION: |
September 2007 |
TOTAL EXPENDED: |
154,126.00$ | |||||||
|
UPDATE SYNOPSIS: |
||||||||||
|
The construction of Wash Rack at the old Litchfield sewer plant is 100% complete. |
||||||||||
Leave a Reply
You must be logged in to post a comment.
