Archive for the 'Capital Improvements' Category

11/05/2007  9:41:44 PM

Improvement updates

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Harry Hartman

 

  

Contact Number:

 

  

623.222.6000

 

Sign Fabrication Shop  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20651  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

42%

 

  

PROJECT BUDGET:

 

901,000.00$  

 

  

EST COMPLETION:

 

  

March 2008

 

  

TOTAL EXPENDED:

 

107,800.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Construction Documents (CD) for the building have been completed and permitted by the State Manufactured Housing Board. Fabrication of the facility has commenced. Becausof the uniqueness of the site and the surrounding areas, the team is seeking direction on how to proceed with the design of the site drainage system.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

City Hall  

 

  

LAST UPDATED:

 

  

10/10/2007

 

  

PROJECT NUMBER:

 

20675  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

53%

 

  

PROJECT BUDGET:

 

60,607,800.00$  

 

  

EST COMPLETION:

 

  

December 2008

 

  

TOTAL EXPENDED:

 

4,203,761.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Project Team has received approved building plans from the Community Development Department and are anticipating Engineering approval the first part of October. Excavation for the building pad for the parking garage has begun.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

Streetscape  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20676  

 

  

CURRENT PHASE:

 

  

CONSTRUCTION

 

  

% COMPLETE:

 

  

99%

 

  

PROJECT BUDGET:

 

5,313,300.00$  

 

  

EST COMPLETION:

 

  

October 2008

 

  

TOTAL EXPENDED:

 

4,085,880.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Streetscape is all but complete, the last of the planting was installed, the fountain was activated, and Flags were hung. The punch list of the last remaining items was also developed in September.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

Central Plant  

 

  

LAST UPDATED:

 

  

10/9/2007

 

  

PROJECT NUMBER:

 

20677  

 

  

CURRENT PHASE:

 

  

CONSTRUCTION

 

  

% COMPLETE:

 

  

99%

 

  

PROJECT BUDGET:

 

8,178,900.00$  

 

  

EST COMPLETION:

 

  

October 2007

 

  

TOTAL EXPENDED:

 

5,922,687.00$  

 

  

UPDATE SYNOPSIS:

 

  

The punch list approximately 90% complete. The last of the landscape that is associated with the Central Plant began installation in September.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Harry Hartman

 

  

Contact Number:

 

  

623.222.6000

 

Fire Station #7  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20702  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

50%

 

  

PROJECT BUDGET:

 

5,317,000.00$  

 

  

EST COMPLETION:

 

  

May 2008

 

  

TOTAL EXPENDED:

 

427,383.00$  

 

  

UPDATE SYNOPSIS:

 

  

The Project Team received the first round of comments from the permit review process. The comments were addressed and resubmitted to the City. The Guaranteed Maximum Price (GMP) was approved by Council Sept 13th.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

Public Works Yard - Deer Valley  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20717  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

0%

 

  

PROJECT BUDGET:

 

10,600,000.00$  

 

  

EST COMPLETION:

 

  

June 2010

 

  

TOTAL EXPENDED:

 

-$  

 

  

UPDATE SYNOPSIS:

 

  

Currently the City’s Water Services Department is developing a site master plan study by which SPA3 (Special Planning Area) will be constructed and expanded over the next several years. As part of the Master Site Plan, an area will be designated for the New Public Works Yard.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Fred Stevens

 

  

Contact Number:

 

  

623.222.6000

 

Bicentennial Park - Enhancement  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20733  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

58%

 

  

PROJECT BUDGET:

 

1,000,000.00$  

 

  

EST COMPLETION:

 

  

June 2008

 

  

TOTAL EXPENDED:

 

149,290.00$  

 

  

UPDATE SYNOPSIS:

 

  

September saw a lot of change come to Bicentennial Park. All of the excess soil from the Lizard Run project, in addition to imported soil, was placed to raise the park play areas. Also, the existing parking lot was removed in preparation for new parking that will extend from the park to the Lizard Run project.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Harry Hartman

 

  

Contact Number:

 

  

623.222.6000

 

Gaines Park Restrooms  

 

  

LAST UPDATED:

 

  

10/1/2007

 

  

PROJECT NUMBER:

 

20802  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

40%

 

  

PROJECT BUDGET:

 

225,000.00$  

 

  

EST COMPLETION:

 

  

January 2008

 

  

TOTAL EXPENDED:

 

3,973.00$  

 

  

UPDATE SYNOPSIS:

 

  

Design and plan review complete. Planned advertising for construction no later than 10/05/07. To council no later than 11/8/07.

 

 

 

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Harry Hartman

 

Contact Number:

 

623.222.6000

Santa Fe Fence 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20803 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

0%

 

PROJECT BUDGET:

440,000.00$ 

 

EST COMPLETION:

 

January 1900

 

TOTAL EXPENDED:

-$ 

 

UPDATE SYNOPSIS:

 

Fence cannot be constructed at this time. Waiting for right-of-way approval by Burlington Northern Santa Fe (BNSF) railroad. City has contacted BNSF and requested approval for placement of fence in their right-of-way. However, this could take 6 months to 2 years for approval.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Dave Kohlbeck

 

Contact Number:

 

623.222.6025

Alley Improvements 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20804 

 

CURRENT PHASE:

 

PROCUREMENT

 

% COMPLETE:

 

0%

 

PROJECT BUDGET:

100,000.00$ 

 

EST COMPLETION:

 

December 2007

 

TOTAL EXPENDED:

-$ 

 

UPDATE SYNOPSIS:

 

Limited response from residents on right-of-way dedication to city. Staff planning on giving council update at the October 23rd meeting with options on how to proceed.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Fred Stevens

 

Contact Number:

 

623.222.6000

Aquatics Facility #3 

 

LAST UPDATED:

 

10/7/2007

 

PROJECT NUMBER:

20806 

 

CURRENT PHASE:

 

PROCUREMENT

 

% COMPLETE:

 

1%

 

PROJECT BUDGET:

650,000.00$ 

 

EST COMPLETION:

 

May 2010

 

TOTAL EXPENDED:

-$ 

 

UPDATE SYNOPSIS:

 

Project Management drafted the Design Services Request for Qualifications (RFQ) for the Aquatic Facility #3. The RFQ has been forwarded to the project’s stakeholders for review and comment.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Kinga Stanek

 

Contact Number:

 

623.222.7037

SPA 1 Installation of Recharge Wells @ South Plant 

 

LAST UPDATED:

 

10/5/2007

 

PROJECT NUMBER:

20234 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

40%

 

PROJECT BUDGET:

4,030,000.00$ 

 

EST COMPLETION:

 

June 2008

 

TOTAL EXPENDED:

310,494.00$ 

 

UPDATE SYNOPSIS:

 

Project Team received 100% drawings and specifications, these are in process of review and final approval for advertisement. Project Team had a pre-application meeting with ADWR (Arizona Department of Water Resources) to initiate review of the application.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Nancy Eberlein

 

Contact Number:

 

623.222.7027

SPA 1 Surprise Center Well Construction 

 

LAST UPDATED:

 

10/8/2007

 

PROJECT NUMBER:

20244 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

52%

 

PROJECT BUDGET:

1,051,600.00$ 

 

EST COMPLETION:

 

December 2007

 

TOTAL EXPENDED:

84,334.00$ 

 

UPDATE SYNOPSIS:

 

Physical construction has begun! Survey completed, Arizona Public Service (APS) conduit run from the ballpark office north to Paradise Lane, concrete has been formed, poured and finished. Underground well equipment will soon follow.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Christine Nuñez

 

Contact Number:

 

623.222.7035

SPA 1 Groundwater Savings Facility Permits 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20415 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

13%

 

PROJECT BUDGET:

430,000.00$ 

 

EST COMPLETION:

 

August 2008

 

TOTAL EXPENDED:

16,450.00$ 

 

UPDATE SYNOPSIS:

 

Project delayed until we can get a meeting with the City of Phoenix to negotiate use on their land

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Todd Gillam

 

Contact Number:

 

623.222.7026

SPA 1 16-in Reclaimed Line Statler to Bell Road Lake 

 

LAST UPDATED:

 

10/2/2007

 

PROJECT NUMBER:

20418 

 

CURRENT PHASE:

 

PROCUREMENT

 

% COMPLETE:

 

8%

 

PROJECT BUDGET:

1,650,000.00$ 

 

EST COMPLETION:

 

December 2009

 

TOTAL EXPENDED:

114,792.00$ 

 

UPDATE SYNOPSIS:

 

The contract has been signed by Dibble Engineering and our Budget Department. The contract is now in the Legal Department awaiting the attorneys’ signature.

 

Department:

 

WATER SERVICES

 

Project Manager:

 

Christine Nuñez

 

Contact Number:

 

623.222.7035

SPA 1 Litchfield Road WRF Decommission 

 

LAST UPDATED:

 

10/1/2007

 

PROJECT NUMBER:

20459 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

98%

 

PROJECT BUDGET:

100,000.00$ 

 

EST COMPLETION:

 

September 2007

 

TOTAL EXPENDED:

31,153.00$ 

 

UPDATE SYNOPSIS:

 

The Litchfield WRF (Water Reclamation Facility) is currently demolished. The City has submitted the clean closure application and is awaiting response/approval of the closure. No change in the past month as the clean closure process may take several months to obtain

11/05/2007  9:40:49 PM

Improvement Updates


11/05/2007  9:29:52 PM

CAPITAL IMPROVEMENT PROJECT UPDATE

  

Department:

 

  

ENGINEERING

 

  

Project Manager:

 

  

Suneel Garg

 

  

Contact Number:

 

  

623.222.3424

 

Right Turn Lane @ Bell & 115th  

 

  

LAST UPDATED:

 

  

10/3/2007

 

  

PROJECT NUMBER:

 

20715  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

40%

 

  

PROJECT BUDGET:

 

1,100,000.00$  

 

  

EST COMPLETION:

 

  

May 2008

 

  

TOTAL EXPENDED:

 

45,561.00$  

 

  

UPDATE SYNOPSIS:

 

  

United Engineering (UE) has been selected to provide the design services. 100% design documents are complete.

 

  

Department:

 

  

ENGINEERING

 

  

Project Manager:

 

  

Nick Mascia

 

  

Contact Number:

 

  

623.222.3400

 

Fiber Optics - Citywide  

 

  

LAST UPDATED:

 

  

10/2/2007

 

  

PROJECT NUMBER:

 

20718  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

10%

 

  

PROJECT BUDGET:

 

750,000.00$  

 

  

EST COMPLETION:

 

  

August 2009

 

  

TOTAL EXPENDED:

 

-$  

 

  

UPDATE SYNOPSIS:

 

  

Consultant contract approved Sept 13, 2007. Design kicked off Sept. 27, 2007.

 

  

Department:

 

  

ENGINEERING

 

  

Project Manager:

 

  

Suneel Garg and Nick Mas

 

  

Contact Number:c

 

  

623.222.3424

 

Historical Lighting Signage for Original Town Site  

 

  

LAST UPDATED:

 

  

10/2/2007

 

  

PROJECT NUMBER:

 

20735  

 

  

CURRENT PHASE:

 

  

PROCUREMENT

 

  

% COMPLETE:

 

  

75%

 

  

PROJECT BUDGET:

 

525,000.00$  

 

  

EST COMPLETION:

 

  

December 2008

 

  

TOTAL EXPENDED:

 

24,837.00$  

 

  

UPDATE SYNOPSIS:

 

  

Street Lights: Arizona Public Service (APS) is currently installing the lights and is estimated to complete by end of October.Decorative Signs and Signals: Council approved the purchase order and new vendor issued notice to proceed to supply signs.

 

  

Department:

 

  

ENGINEERING

 

  

Project Manager:

 

  

Suneel Garg

 

  

Contact Number:

 

  

623.222.3424

 

Cotton Lane Widening (North of Bell Road)  

 

  

LAST UPDATED:

 

  

10/3/2007

 

  

PROJECT NUMBER:

 

20807  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

45%

 

  

PROJECT BUDGET:

 

300,000.00$  

 

  

EST COMPLETION:

 

  

June 2008

 

  

TOTAL EXPENDED:

 

-$  

 

  

UPDATE SYNOPSIS:

 

  

The project is placed for bid closing Oct 11.

 

  

Department:

 

  

ENGINEERING

 

  

Project Manager:

 

  

Suneel Garg

 

  

Contact Number:

 

  

623.222.3424

 

Litchfield Road (Bell Road to Statler Boulevard)  

 

  

LAST UPDATED:

 

  

10/2/2007

 

  

PROJECT NUMBER:

 

20808  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

45%

 

  

PROJECT BUDGET:

 

1,300,000.00$  

 

  

EST COMPLETION:

 

  

May 2008

 

  

TOTAL EXPENDED:

 

-$  

 

  

UPDATE SYNOPSIS:

 

  

Improve Litchfield Road from Bell Road to Statler Boulevard a distance of approximately 1/2 mile. 100% plans are complete and approved. Arizona Public Services (APS) is in the process of finalizing the street light plans

 

  

Department:

 

  

ENGINEERING

 

  

Project Manager:

 

  

Suneel Garg

 

  

Contact Number:

 

  

623.222.3424

 

Reems Road (Waddell Road to Peoria Avenue)  

 

  

LAST UPDATED:

 

  

10/3/2007

 

  

PROJECT NUMBER:

 

20809  

 

  

CURRENT PHASE:

 

  

DESIGN

 

  

% COMPLETE:

 

  

37%

 

  

PROJECT BUDGET:

 

9,500,000.00$  

 

  

EST COMPLETION:

 

  

July 2008

 

  

TOTAL EXPENDED:

 

-$  

 

  

UPDATE SYNOPSIS:

 

  

100% improvement plans are complete. Waiting for the approval from Maricopa Water District (MWD) for the irrigation channel relocation.

 

  

Department:

 

  

ENGINEERING

 

  

Project Manager:

 

  

Nick Mascia

 

  

Contact Number:

 

  

623.222.3400

 

Traffic Signals  

 

  

LAST UPDATED:

 

  

10/2/2007

 

  

PROJECT NUMBER:

 

29999  

 

  

CURRENT PHASE:

 

  

Various Stages

 

  

% COMPLETE:

 

  

0%

 

  

PROJECT BUDGET:

 

7,477,400.00$  

 

  

EST COMPLETION:

 

  

Various Stages

 

  

TOTAL EXPENDED:

 

3,506,008.00$  

 

  

UPDATE SYNOPSIS:

 

  

This project has various intersections at various stages of design, procurement, and construction. The detail portion will provide the specific information on each intersection.

 

  

Department:

 

  

PUBLIC WORKS

 

  

Project Manager:

 

  

Terry Lowe

 

  

Contact Number:

 

  

623.222.6000

 

Public Safety Building  

 

  

LAST UPDATED:

 

  

10/7/2007

 

  

PROJECT NUMBER:

 

20219  

 

  

CURRENT PHASE:

 

  

CONSTRUCTION

 

  

% COMPLETE:

 

  

99%

 

  

PROJECT BUDGET:

 

31,701,300.00$  

 

  

EST COMPLETION:

 

  

October 2007

 

  

TOTAL EXPENDED:

 

25,388,175.00$  

 

  

UPDATE SYNOPSIS:

 

  

The entire construction of the Public Safety Facility is 98%. The last 2% accounts for the punch list and any misc. items that are as of yet unresolved. The Fire Department, the Court and Prosecution were relocated into the Facility in September. The Grand Opening is scheduled for Saturday, November 3rd.

 

 

 

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Terry Lowe

 

Contact Number:

 

623.222.6000

Lizard Run Pedestrian Walkway 

 

LAST UPDATED:

 

10/7/2007

 

PROJECT NUMBER:

20517 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

58%

 

PROJECT BUDGET:

1,023,800.00$ 

 

EST COMPLETION:

 

June 2008

 

TOTAL EXPENDED:

124,923.00$ 

 

UPDATE SYNOPSIS:

 

The contractor has completed the mass grading of the site. This involves staking the site to identify the final elevations and the project area then shaping the earth accordingly. Excavation commenced for the installation of the sidewalk and gabion wall. In addition, all drywells for the site have been installed.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Harry Hartman

 

Contact Number:

 

623.222.6000

Fire Station #6 

 

LAST UPDATED:

 

10/7/2007

 

PROJECT NUMBER:

20559 

 

CURRENT PHASE:

 

CONSTRUCTION

 

% COMPLETE:

 

100%

 

PROJECT BUDGET:

4,990,000.00$ 

 

EST COMPLETION:

 

August 2007

 

TOTAL EXPENDED:

4,297,675.00$ 

 

UPDATE SYNOPSIS:

 

The Grand Opening for the FS306 took place September 22nd.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Harry Hartman

 

Contact Number:

 

623.222.6000

Fire Station #5 

 

LAST UPDATED:

 

10/7/2007

 

PROJECT NUMBER:

20602 

 

CURRENT PHASE:

 

CONSTRUCTION

 

% COMPLETE:

 

98%

 

PROJECT BUDGET:

5,870,000.00$ 

 

EST COMPLETION:

 

October 2007

 

TOTAL EXPENDED:

5,058,992.00$ 

 

UPDATE SYNOPSIS:

 

The construction of the Fire Station is approximately 95% complete. Final testing and inspections were completed in September. The Fire Department is scheduled to occupy the facility on the 1st of October. The Grand Opening has been set for Saturday, October 13th.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Terry Lowe

 

Contact Number:

 

623.222.6000

Surprise Farm Park Development 

 

LAST UPDATED:

 

10/10/2007

 

PROJECT NUMBER:

20606 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

39%

 

PROJECT BUDGET:

5,620,000.00$ 

 

EST COMPLETION:

 

January 2009

 

TOTAL EXPENDED:

305,889.00$ 

 

UPDATE SYNOPSIS:

 

The modification of the scope of the project for Surprise Farms Park require additional design services to be put forth. These additional services will be brought before council on October 23rd for approval. The modifications to the scope have lead to a delay in the project’s schedule.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Terry Lowe

 

Contact Number:

 

623.222.6000

Skate/Bike Park 

 

LAST UPDATED:

 

10/7/2007

 

PROJECT NUMBER:

20618 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

28%

 

PROJECT BUDGET:

950,000.00$ 

 

EST COMPLETION:

 

June 2008

 

TOTAL EXPENDED:

14,172.00$ 

 

UPDATE SYNOPSIS:

 

The City received the 60% design documents from the designer in September. Comments will be generated by the Project Management Division (PMD) and returned to the designer in October.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Harry Hartman

 

Contact Number:

 

623.222.6000

Fire Station #2 Remodel 

 

LAST UPDATED:

 

10/10/2007

 

PROJECT NUMBER:

20624 

 

CURRENT PHASE:

 

PROCUREMENT

 

% COMPLETE:

 

75%

 

PROJECT BUDGET:

769,200.00$ 

 

EST COMPLETION:

 

February 2008

 

TOTAL EXPENDED:

35,138.00$ 

 

UPDATE SYNOPSIS:

 

The exterior site improvements for the Station were completed in September. Council gave approval to the GMP for the interior remodel which commenced towards the end of the month. Presently, the existing interior partitions are being demolished. Demolishing should continue into October.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Terry Lowe

 

Contact Number:

 

623.222.6000

Public Safety Park Development 

 

LAST UPDATED:

 

10/10/2007

 

PROJECT NUMBER:

20635 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

39%

 

PROJECT BUDGET:

200,000.00$ 

 

EST COMPLETION:

 

January 2009

 

TOTAL EXPENDED:

20,000.00$ 

 

UPDATE SYNOPSIS:

 

The modification of the scope of the project for Surprise Farms Park require additional design services to be put forth. These additional services will be brought before council on October 23rd for approval. The modifications to the scope have lead to a delay in the project’s schedule.

 

Department:

 

PUBLIC WORKS

 

Project Manager:

 

Harry Hartman

 

Contact Number:

 

623.222.6000

Wash Racks 

 

LAST UPDATED:

 

10/9/2007

 

PROJECT NUMBER:

20645 

 

CURRENT PHASE:

 

DESIGN

 

% COMPLETE:

 

100%

 

PROJECT BUDGET:

180,000.00$ 

 

EST COMPLETION:

 

September 2007

 

TOTAL EXPENDED:

154,126.00$ 

 

UPDATE SYNOPSIS:

 

The construction of Wash Rack at the old Litchfield sewer plant is 100% complete.

 

 